1. My first two immediate jobs
that I need to continue when I moved to the newly formed 2-staff EE unit
in the end of 2007 were the processing the application for fiscal
incentives on EE projects and products and soon after that, I was instructed to
prepare the implementation strategy and plan for the enforcement of the new
Efficient Management of Electrical Energy Regulations which finally was
gazetted on 15 December 2008.
2. Not long after that, the Budget Speech for the
year 2009 added one more challenging test for me where suddenly the fiscal
incentives for EE was extended to more products approved by Energy Commission
effective from 31 August 2008.
3. In the end of 2007 and
early 2008, I spent a lot of time asking people who were in-charge of every
previous tasks under the disbanded EE department. It became more challenging
because most of all the detailed documents and information were not at one
place in dedicated files. The handing over notes that I received was very
brief an I had to meet and speak personally to individuals who are in
various department to get the whole picture on the historical information and
progress of each tasks.
Incentives for EE Projects and Products
4. When I tried to understand
to whole process of the EE& RE incentives application, the procedure
required me to perform the assessment of each application and later to
call for a committee to present the initial assessment and later to call pre-selected
applicants for a presentation. There were brief guidelines prepared for potential applicants but most of the applications received were not following it and I had to contact each applicant personally asking about information and data required for the the initial assessment.
5. We received all sorts of application which some of them were quite difficult the EE element that qualify them for the incentives mainly due to lacking of EE related key information and data for proposed EE projects and products.
6. To improve this and to save more time to assess each application, I drafted the evaluation guidelines for EE project and products with the intention to upload it the public domain in our website and to be circulated to other agencies such as MIDA and KeTTHA for their information and reference. I tried to impart and integrate my knowledge and real life experiences in EE projects and products in the guidelines and in the same time not to make it too difficult for potential applicants.
7. Below are the two guidelines which finally approved by the management and later published and promoted to the interested parties.
for EE Projects
GUIDELINES ON
THE INFORMATION REQUIRED FOR
THE TECHNICAL EVALUATION OF ENERGY EFFICIENCY
PROJECTS
Please
attach the information with completed MIDA’s application form. The information
to be submitted may vary depending on the type/complexity/scale of the
projects. Kindly contact Energy Commission
at Tel: 03-2612 5400/554/536 or Fax
03-26912654 should there be any query.
PART A : TYPE OF PROJECT
|
· Modification/improvement
of existing equipment/systems or
· Introduction/replacement
of high efficient technologies or systems.
|
PART B : GENERAL INFORMATION OF THE
PLANT/EQUIPMENT
AND
ITS ENERGY CONSUMPTION
|
1
.Name and location.
|
2.
Types of energy supplied.
|
3.
Tariff/rates applied (fuel, electricity).
|
4.
Energy consumption per year such as electricity and fuel.
|
5.
Plant/equipment energy performance such as
efficiency level and etc.
|
PART C : INFORMATION ON THE ENERGY
EFFICIENCY PROJECT/EQUIPMENT
|
1.
Description on the equipment/system technologies to be applied.
|
2.
Operational principles/systems applied to improve efficiency and to save energy.
|
3.
A schematic drawings/diagrams showing the facilities, equipment and processes
involved.
|
4.
Equipment/System Information:
|
5.
Energy efficiency/energy performance standard referred.
|
6.
Testing standard used and its test
reports.
|
7.
Function of each equipment contributing to increase its efficiency and to save
energy.
|
8.
Comparison of technical and efficiency
data between existing or conventional plant /equipment and proposed plant/equipment.
|
PART D : ENERGY
CONSERVATION POTENTIALS
|
1. Types of energy to be saved.
|
2. Comparison of energy consumption data between
existing or conventional plant /equipment and proposed plant/equipment.
|
3. Method and data used in energy saving the calculations.
|
4. Estimated energy savings from electricity
and/or fuel consumption in energy units.
|
PART E : IMPLEMENTATION PLAN
|
1.
Who will be involved in the implementation of the project (i.e. Internal
personnel/external)
|
2. Brief description on steps to be taken to
implement the project and the targeted duration for implementation.
|
PART F : COSTS OF THE PROJECT
|
1. The
total costs and itemized cost for each equipment involved.
2. Estimated energy costs to be saved and returns of the
investment for the project (i.e. Simple Payback Period, IRR)
|
For EE Products
GUIDELINES ON
THE INFORMATION REQUIRED FOR THE
TECHNICAL EVALUATION OF ENERGY EFFICIENCY AND
RENEWABLE ENERGY PRODUCTS FOR IMPORTERS AND LOCAL MANUFACTURERS
PART
A :TYPE OF APPLICANT
|
1.
Producer/Manufacturer Or
2.
Authorised Agent/Distributor/Importer/APVSP(for PV systems)
|
PART
B : INFORMATION OF ENERGY EFFICIENT
EQUIPMENT/APPLIANCE/MATERIAL
|
1. Product Description
|
2. Brand and Model
|
3. Energy Efficiency
Rating
|
4. Energy Efficiency Reference Standard Used
|
5. Testing Standard Used
|
6. Producer/Manufacturer
|
7. Product Application
|
PART
C : SUPPORTING DOCUMENT/INFORMATION
|
1.
Letter/Certificate of authorization to
produce/manufacture
|
2.
Letter/Certificate as authorized importer/agent/distributor
|
3.
Confirmation on energy efficiency
|
Kindly contact Energy
Commission at Tel: 03-2612 5536/32 or
Fax 03-26912654 should there be any query.
8. When I started for EE products, I found
out only 2 types of products already had their EE criteria and labeling
scheme to be classified as energy efficient products.
9. I was in tremendous pressure when manufacturers for other type of products already called us to apply for incentives since the Budget 2009 speech clearly stated that the effective date was on 31 August 2008 and we only knew about it on the day the budget speech read by the PM. This has led me to rush quickly to request for more information from MoF and MIDA before I can start to answer queries with regard to the incentives.
10. What I did finally with all the updated information was, told the manufacturers and importers that we just knew about it and need some time to prepare the criteria to qualify products covered under the budget speech. I invited them together with other relevant industrial & Professional organizations such as FMM,MEADA, and MASHRAE and also SIRIM to assist me to develop and agree on EE Criteria to be established for each type of products because that was the only way for them to enjoy the incentives at soonest possible.
11. Working Groups were formed to look after each type of product and I personally chaired each of them and acted as the desk officer too for each group who compiled and analyzed all information and data to be discussed in the scheduled meetings.
There were days we had to have 3 meetings for different groups in a day and finally some products were able to be qualify in stages from early 2009.
12. From 2 type of products in August 2008, within 6 months, we already had 8 types can be classified as energy efficient and manufacturers were able to apply to enjoy the incentives. All can be done and we did it by working hand in hand with everyone.
13. With the published guidelines on our website, I had better time to explain to questions related to EE incentive application and asked them to the evaluation criteria for application purposes. This has made the processing smoother and faster because almost all key information and data were already available when application received instead to chase them to submit it previously.
14. On top of that, I had the chance to share the latest updates on the incentive application procedure and evaluation criteria personally too as guest speakers to events such as talks and briefing in seminar, dialogues and forum for different target groups organized internally and by other related parties.
Briefing on EE Incentives Application & Evaluation Process |
The Implementation Plan for Efficient Management of Electrical Energy Regulations
15. This regulation has a long and personal historical link to my career from the beginning.Finally, it was about to be gazetted and I was instructed to prepare the overall implementation plan which to be presented to the ministry for approval before the effective date.
16. This was the most challenging of all the tasks assigned to me in EE Unit. I really had to dig deep from many references and utilizing all that I have in me as EE practitioner in the market previously and later my involvement in regulatory works in the legal department. All that knowledge and hands-on experiences helped me a lot because literally no one has ever implemented this type of regulations in Malaysia to refer. References from success stories and obstacles in implementing this type of law in countries such as Japan and India also helped me a lot in coming up with the plan for Malaysia.
17. Below are the my initial checklist that I personally developed on my own for the early stage of preparing the plan ( at this time there were still only me and my clerk in the unit).
PERINCIAN
PERSEDIAAN YANG DIPERLUKAN UNTUK PERLAKSANAAN PERATURAN-PERATURAN PENGURUSAN
TENAGA ELEKTRIK DENGAN CEKAP 2008
PERKARA
|
TINDAKAN/MAKLUMAN
|
|
1
|
Perlaksanaan
berdasarkan peruntukan-peruntukan dalam peraturan
|
·
Sediakan draf flowchart
|
2
|
Peraturan
6 :Pemberitahuan oleh
Suruhanjaya
|
·
Draf
notis pemberitahuan kepada pepasangan
|
3
|
Peraturan 7 : Obligasi pemegang lesen persendirian/pengguna
Mengemukakan maklumat-maklumat seperti yang dikehendaki dalam Peraturan 6 berkenaan:-
i)
Dasar
ii)
Matlamat
iii)
Akaun/maklumat
|
·
Menyediakan
garis panduan skop dasar , matlamat dan akaun/maklumat yang dikehendaki
|
4
|
Peraturan 11 : Pendaftaran pengurus tenaga elektrik
i)
Proses
permohonan – flowchart
ii)
Buku
panduan
|
·
Sediakan draf flowchart
·
Draf kandungan buku panduan pendaftaran
|
5
|
Peraturan 12 : Kehendak kelayakan
i)
Syarat-syarat
kelayakan
23 tahun ke atas , warganegara Malaysia
·
Jurutera
profesional
6 bulan pengalaman kerja dalam pengurusan tenaga
elektrik dengan cekap
·
Ijazah sains, kejuruteraan, senibina atau setaraf
1 tahun pengalaman kerja dalam pengurusan tenaga
elektrik dengan cekap
·
Jurutera Perkhidmatan
Elektrik(JPE)/Jurutera Elektrik(JEK) Kompeten
9 bulan pengalaman kerja dalam pengurusan tenaga
elektrik dengan cekap
·
Pengetahuan berkenaan Akta dan Peraturan
ii)
Temuduga
|
·
Untuk JPE, laporan projek/tugasan berkenaan pengurusan tenaga dengan cekap
merupakan salah satu keperluan yang
perlu dipenuhi sebelum pendaftaran diluluskan oleh ST(Peraturan 46(2)(a), PPE
1994). Peruntukan yg sama ada untuk JEK tetapi tidak dilaksanakan lagi
· Kriteria penilaian
pengalaman kerja dalam pengurusan tenaga elektrik dengan cekap
· Kriteria penilaian dalam
temuduga
· Pemilihan dan perlantikan
ahli panel penemuduga
· Buku panduan skop pengetahuan dan pengalaman kecekapan tenaga dan perundangan
yang berkaitan untuk rujukan bakal pemohon
|
6
|
Peraturan 13 : Permohonan pendaftaran
iii)
Fi
Jadual pertama
Perwakilan kuasa untuk menerima fi oleh pejabat kawasan
iv)
Borang – maklumat dan dokumen sokongan yang diperlukan
|
·
Draf surat perwakilan kuasa
·
Draf borang permohonan
|
7
|
Peraturan 14 : Pengeluaran perakuan pendaftaran
i)
Sijil perakuan pendaftaran
|
|
8
|
Peraturan 15 : Keterangan perubatan kesihatan pemohon
i)
Dokumen
pengesahan keterangan perubatan
|
|
9
|
Peraturan 16 : Fungsi dan kewajipan pengurus
tenaga elektrik berdaftar
i)
Mengaudit
ii)
Menasihati pemegang lesen
iii)
Memantau keberkesanan
iv)
Menyelia penyimpanan rekod pengurusan tenaga elektrik
dengan cekap
v)
Mempastikan pengguna/pemengang lesen mengemukakan
laporan dalam Peraturan 6 dalam tempoh seperti dalam Peraturan 7.
|
·
Panduan komponen-komponen utama dalam laporan audit
·
Definisi/penerangan/skop audit tenaga yang dimaksudkan.
· Panduan jenis-jenis rekod yang dikehendaki
|
Skop tugas
i)
Makluman kepada pengguna/pemegang lesen terlibat
ii) Pendaftaran
iii) Penerimaan bayaran fi
iv) Borang laporan setiap enam bulan daripada
pengguna/pemegang lesen.
|
·
Edaran borang permohonan
·
Penerimaan borang permohonan
·
Proses borang permohonan
·
Panggilan temuduga
·
Jalankan temuduga
· Daftarkan dan maklumkan calon yang lulus permohonan
·
Keluarkan sijil kelulusan pendaftaran
· Semakan dan penilaian laporan
·
Kriteria penilaian
·
Tindakan jika terdapat ketidakpatuhan
|
Below is the initial implementation timeline for the implementation of the regulations
18. There were only two of us in the unit and I strongly believe we have accomplished something very significant and satisfying for the whole year. I must thank everyone who was there to assist and support me all the way and that gave more motivation that I can contribute more in EE for the country.
19. 2008 was the first full year for me doing EE works in Energy Commission and what I had accomplished did make more inspired to go further.
20. I hope to have the time to share some significant events that led to my involvement in the preparation of the National EE Master Plan way back when it started from 2008 and below are the summary of key activties reported to the management for that year.
RINGKASAN LAPORAN AKTIVITI
TAHUNAN UNIT DEMAND SIDE MANAGEMENT 2008
1. Peraturan-Peraturan
Pengurusan Tenaga Elektrik Dengan Cekap 2008.
Unit DSM telah menyediakan pelan tindakan untuk
melaksanakan Peraturan-Peraturan
Pengurusan Tenaga Elektrik Dengan Cekap telah diwartakan dan
dikuatkuasakan pada 15 Disember 2008.
Di antara perkara-perkara yang
telah dijalankan ialah penyediaan
perincian pelan tindakan dan penyediaan keperluan-keperluan untuk pelaksanaan peraturan tersebut seperti sistem
pendaftaran, borang, kriteria pemilihan pengurus tenaga, penilaian laporan dan
lain-lain lagi.
2. Kumpulan
Kerja Untuk Menetapkan Kriteria dan Standard Rujukan Kecekapan Tenaga
Beberapa kumpulan kerja untuk bahan dan kelengkapan cekap tenaga
telah ditubuhkan untuk tujuan pemberian
insentif kecekapan tenaga kepada pengimport
dan pengeluar tempatan seperti yang telah diumumkan di dalam Bajet 2009.
Kumpulan-kumpulan kerja berkenaan telah ditubuhkan
dengan disertai oleh wakil-wakil
pengeluar, SIRIM, PTM, FMM dan pertubuhan-pertubuhan profesional dan industri
yang berkaitan dan di antara objektif utama penubuhannya ialah:
- Mengesyorkan kriteria prestasi kecekapan tenaga standard rujukan yang boleh digunapakai;
- Menetapkan syarat-syarat pengujian untuk pengesahan kriteria prestasi tenaga yang telah ditetapkan;
- Menyediakan sistem penarafan untuk menilai prestasi kecekapan tenaga bahan/kelengkapan tertentu.
Kumpulan kerja yang ditubuhkan
untuk bahan dan kelengkapan berikut:
i) Bahan Penebat;
ii) Kipas domestik;
iii)Penyaman Udara;
iv)Lampu;
v) Televisyen
3. Insentif Kecekapan Tenaga.
i) Proses permohonan insentif.
Unit DSM telah memproses sejumlah
22 permohonan insentif kecekapan tenaga. Permohonan insentif berkenaan
adalah merangkumi permohonan pengecualian cukai jualan dan duti import,
permohonan sebagai status perintis dan juga elaun cukai pelaburan. Unit
DSM bertanggungjawab sebagai Urusetia
untuk Jawatankuasa Penilaian Teknikal Untuk Insentif Kecekapan Tenaga dan menjalankan proses penilaian teknikal untuk setiap
permohonan.
ii) Unit DSM juga telah menjadi ahli jawatankuasa kumpulan kerja yang ditubuhkan
oleh Kementerian Tenaga, Air dan Komunikasi untuk menyediakan buku panduan
permohonan insentif kecekapan tenaga dan tenaga boleh diperbaharui untuk
rujukan pihak industri.
4. Penarafan Prestasi Kecekapan Tenaga Untuk Peti Sejuk
Unit DSM telah memproses dan
meluluskan 13 permohonan pengeluar untuk
mendapatkan penarafan STAR untuk peti sejuk berdasarkan prestasi kecekapan
tenaga. Sebanyak dua belas model peti sejuk telah mendapat kelulusan dengan penarafan 5 STAR dan satu model
mendapat penarafan 3 STAR.
5. Promosi Dan Kempen
i) Unit DSM telah menjadi ahli jawatankuasa pemandu Kempen Kesedaran Kecekapan Tenaga
Nasional dan Bulan Tenaga 2008 di peringkat Kementerian
Tenaga, Air dan Komunikasi. Pelancaran kedua-dua program
tersebut telah diadakan pada bulan November 2008.
ii) Taklimat dan ceramah kecekapan tenaga seperti
berikut telah disempurnakan oleh Unit DSM.
· Workshop on EE & RE Handbook for
Fiscal Incentives anjuran
Kementerian Tenaga, Air dan Komunikasi;
· Workshop On High Efficiency Motors
anjuran Pusat Tenaga Malaysia;
· Kempen Kecekapan Tenaga Dan Keselamatan Elektrik anjuran pejabat Kawasan Suruhanjaya Tenaga
Ipoh.
· Kursus Polisi dan Aplikasi Kecekapan Tenaga anjuran Jabatan Pengairan dan
Saliran;
· Seminar Kecekapan Tenaga
anjuran TNB Kuantan; dan
· Seminar Kecekapan Tenaga Dan
Keselamatan Elektrik Untuk Kakitangan Pihak Berkuasa Tempatan Selangor anjuran pejabat Kawasan Suruhanjaya
Tenaga Petaling Jaya.
6. Pembangunan Kakitangan
Penyertaan di dalam program
berikut:
i) Training Program on Renewable Energy and Energy Efficiency anjuran
Technical Energy Research Institute(TERI)
dan Kementerian Luar India di
TERI di Gual Pahari dan Bangalore,India;
At TERI Gual Pahari, India |
ii) Training
Program on Energy Conservation for
Malaysia anjuran Kementerian Ekonomi, Perdagangan dan Industri Jepun di Energy Conservation Centre, Tokyo,Jepun;
At AOTS-Kita-senju Tokyo |
iii) Logical Framework Analysis Workshop
on Building Energy Efficiency anjuran JKR dan UNDP di Kuala Lumpur;
iv) National Photovoltaic Conference anjuran
Pusat Tenaga Malaysia dan UNDP di Putrajaya; dan
v) Seminar On Promotion Of Energy Efficiency And Conservation (PROMEC) for
Buildings anjuran Pusat Tenaga
Malaysia dan EISD/PROMECC 2008 di Seri
Kembangan.